Discovery Outputs and Readiness Review
DOCUMENT CATEGORY: Runbook SCOPE: Discovery outputs and readiness review PURPOSE: Define deliverables and review procedures MASTER REFERENCE: Microsoft Learn - Azure Local Planning
Status: Active
This section covers the required outputs from discovery sessions and the readiness review process for implementation.
Required Outputs from Discovery
Master Deliverables Package
- Configuration Workbook (Excel):
- Naming standards worksheet
- Network configuration worksheet
- IP allocation worksheet
- VLAN assignment worksheet
- Workload inventory worksheet
- Migration grouping worksheet
- Design Documents:
- High-level design (HLD) with deployment specifics
- Low-level design (LLD) with implementation details
- Network architecture diagram
- Application dependency map
- Implementation Plan:
- Detailed project timeline
- Resource allocation schedule
- Migration wave planning
- Risk mitigation strategies
- Configuration Files (Pre-staged):
- Network switch configurations
- Firewall rule sets
- PowerShell deployment scripts
- ARM templates (customized)
Readiness Review with Implementation Team
Readiness Review Agenda
- Review Discovery Findings (30 min)
- Requirements summary
- Technical constraints and considerations
- Risk areas identified
- Configuration Walkthrough (45 min)
- Naming standards implementation
- Network design specifics
- Azure resource configuration
- Security requirements
- Implementation Planning (30 min)
- Timeline confirmation
- Resource availability
- Stakeholder touchpoints
- Escalation procedures
- Q&A and Clarifications (15 min)
Implementation Team Receives
- Complete discovery documentation package
- Access to documentation repository and configuration files
- Contact information for key stakeholders
- Escalation matrix for issues
Discovery Data Validation
Before final review, validate all collected data for accuracy and completeness. Ensure all configuration parameters have been confirmed with stakeholders and no assumptions remain.
Post-Discovery Actions
Final Review and Preparation
Post-Discovery Review Meeting
Participants: Same as pre-discovery team
Agenda:
- Review all collected data for completeness
- Identify any gaps or clarifications needed
- Finalize implementation approach
- Confirm resource assignments
- Update project timeline based on findings
Action Items:
- Update configuration templates with deployment data
- Prepare network switch configurations
- Stage PowerShell scripts with deployment variables
- Create deployment-specific runbooks
- Schedule implementation kickoff
Stakeholder Communication
Discovery Summary Communication
Subject: Azure Local - Discovery Complete - [Organization Name]
Dear [Stakeholder],
We have completed the discovery sessions for your Azure Local implementation.
Attached please find:
1. Discovery Summary Document
2. Proposed Configuration Settings
3. Network Design Diagram
4. Implementation Timeline
Key Decisions Confirmed:
- Naming Convention: [Pattern]
- Network VLANs: [List]
- IP Ranges: [Ranges]
- Target Go-Live: [Date]
Next Steps:
- Please review and confirm the attached configuration
- Identify any changes needed within 48 hours
- Schedule implementation kickoff meeting
The implementation team is prepared to begin deployment upon your approval.
Best regards,
[deployment team]
Discovery Phase Completion Gate
- All discovery data collected and validated
- Naming standards finalized and documented
- Network requirements confirmed and allocated
- Stakeholder sign-off obtained
- Implementation team briefed and ready
- Hardware and Azure resources ready for provisioning
With comprehensive discovery data collected, validated, and approved, the implementation team can proceed confidently to hardware and infrastructure provisioning with all required configuration details in hand.
As part of the discovery phase, the implementation team must produce and validate the following configuration artifacts:
- Cluster Configuration File
- Cluster Automation Config File
These documents are required for handoff to the implementation team and must be referenced in all subsequent deployment planning and execution steps.